Construction of RCC Boundry Wall to Seperate Using Solid Block With 20Cm Thick RCC Floor Slab
Construction of RCC Boundary Wall to Separate Using Solid Block with 20 cm Thick RCC Floor Slab
Thi...
Construction Of 132KV
Project Name : Additionroofing, Chain Pulley, Heat Ventilation Works for Shunt
Reactor at 132KV Uni...
11KV Substation Foundation
Project Name
Construction of 11KV Substation Foundation (485cm*485cm)
Location : Sharjah Power D...
Construction Of 11Kv Substation
When it's about controlling hundreds of articles, product pages for web shops, or user profiles in social networks, all
AL Sajja – Sewa Maintenance
Project Name :Civil Maintenance Works of 220/132 KV Sajja SubstationLocation : Al SajjaClient :SEWA...
AL Wasit – Sewa Maintenance
Project Name : Civil Maintenance Works of 220/132/33 KV Wasit SubstationLocation : Al HomahClient :S...
Khorfakkan Sewa Maintenance
Project Name : Maintenance for Khorfakkan Department Office Location : Khorfakkan Power Distribution...
Sewa Water Tank Maintenance
Project Name : To Carry out General Maintenance for Two Numbers of RCC Tanks with(35 meter diameter ...
Sewa Material Supply
Project Name :Location : Sharjah Power DistributionClient : SEWAP.O. :SPD/L/23/0082486